What Size Solar Breaker Can You Back-Feed Into a 225 A Panel With a 125 A Main?

Short answer: 125 A. On a 225 A busbar with a 125 A main, NEC 705.12(B)'s 120% allowance is 270 A, leaving 145 A for the solar breaker — which supports roughly a 24 kW inverter at 240 V.

The rule, applied to this panel

NEC 705.12(B)(3)(2) — the "120% rule" — lets the busbar rating × 1.2 be shared between the main breaker and the sum of back-fed supply breakers, provided the solar breaker sits at the opposite end of the busbar from the main.

Every breaker size on this configuration

Back-fed breakerMain + back-fed120% allowanceHeadroomResult
15 A140 A270 A130 Aallowed
20 A145 A270 A125 Aallowed
25 A150 A270 A120 Aallowed
30 A155 A270 A115 Aallowed
35 A160 A270 A110 Aallowed
40 A165 A270 A105 Aallowed
45 A170 A270 A100 Aallowed
50 A175 A270 A95 Aallowed
60 A185 A270 A85 Aallowed
70 A195 A270 A75 Aallowed
80 A205 A270 A65 Aallowed
90 A215 A270 A55 Aallowed
100 A225 A270 A45 Aallowed
125 A250 A270 A20 Aallowed

Before you rely on this

Passing the arithmetic is necessary but not sufficient. The solar breaker must be at the opposite end of the busbar from the main — that physical placement is what the 120% allowance is premised on, because it keeps the busbar from carrying both sources across its full length. The panel also needs the 705.12(B)(3) warning stating the busbar is fed from multiple sources and the breaker must not be relocated. A reviewer who sees correct arithmetic and no placard will still red-line the set.

If 125 A is not enough for your inverter, the options below apply just as they would to a failing calculation.

Where the 120% rule does not get you there, these are the code-compliant routes:

Related

Checking a real interconnection? OneLine Studio runs this exact calculation live while you draw — and every other one the plan reviewer will check — then prints it into a 10-sheet permit set with the manufacturer datasheets already attached. Describe your system in a sentence and the first one is free: open the studio.

Computed with OneLine Studio's NEC engine — the same deterministic code tables that size a real permit set, not an estimate. Conductor ampacity from NEC 310.16, correction factors from 310.15(B)(1), fill adjustment from 310.15(C)(1). Always confirm the enforced NEC edition and any local amendments with your AHJ.

FAQ

What is the largest solar breaker I can back-feed into a 225 A panel with a 125 A main?

125 A. The 120% allowance is 270 A, the main uses 125 A, leaving 145 A — so 125 A is the largest standard breaker that fits.

What size inverter does that support?

Roughly 24 kW at 240 V single phase. A back-fed breaker must be at least 125% of the inverter's continuous output current, so a 125 A breaker supports about 100 A of continuous output.

Why does the breaker have to be at the opposite end of the busbar?

The 120% allowance assumes the two sources feed from opposite ends, so no single section of busbar carries the full combined current. Relocating the breaker defeats that assumption, which is exactly why 705.12(B)(3) requires a permanent label warning against it.

Educational reference, reviewed 2026-07. A design aid, not a substitute for a licensed electrician or PE. Confirm the enforced NEC edition and local amendments with your AHJ.