Sheet 1 of 11 · The contract with the reviewer
Cover
Before a reviewer checks a single wire, they check whether this set is even reviewable — for the right house, under the right code edition.
Sheet 1 · Cover — schematic
Sheet 2 of 11 · Where it lives, and how a firefighter gets to it
Site / Plot Plan
Two drawings in one: the property from above, and the roof up close. One proves the system fits the lot legally; the other proves someone can walk on that roof during a fire.
Sheet 2 · Site / Plot Plan — schematic
Sheet 3 of 11 · Will the roof hold, and will the wind take it
Structural & Uplift
Solar adds weight for 25 years and gives wind something to grab. This sheet is where a roof is proven capable — or honestly flagged as needing an engineer.
Sheet 3 · Structural & Uplift — schematic
Sheet 4 of 11 · The sheet reviewers read hardest
Three-Line Diagram
Every conductor, every device, every rating — from the first cell in the array to the utility's meter. If one sheet gets scrutinized line by line, it's this one.
Sheet 4 · Three-Line Diagram — schematic
Sheet 5 of 11 · So the next person can read it
Color-Coded Wiring
The same system as Sheet 4, drawn the way an electrician's eye works: by color, by conductor kind, by what's carrying power versus data.
Sheet 5 · Color-Coded Wiring — schematic
Sheet 6 of 11 · The bill of materials that has to be true
Equipment & Circuit Schedules
Tables where every device gets a quantity, a model, a rating and a UL listing — and every circuit gets its conductor, its breaker and its conduit fill.
Sheet 6 · Equipment & Circuit Schedules — schematic
Sheet 7 of 11 · Written for someone you'll never meet
Label & Placard Schedule
Every placard, its exact wording and where it goes. These labels are read by a firefighter at 3 a.m. and an electrician a decade from now.
Sheet 7 · Label & Placard Schedule — schematic
Sheet 8 of 11 · The design grading itself
NEC Compliance Review
An itemized pass/fail against the code sections that actually get cited — each with the number, the math, and the verdict.
Sheet 8 · NEC Compliance Review — schematic
Sheet 9 of 11 · Can the house actually take this
Service Load Calculation
The dwelling's demand, itemized the way an inspector re-derives it — because they will.
Sheet 9 · Service Load Calculation — schematic
Sheet 10 of 11 · The other approval you need
Utility Interconnection
The AHJ approves the building work. The utility approves connecting to their grid. Two separate reviews — this sheet feeds the second.
Sheet 10 · Utility Interconnection — schematic
Sheet 11 of 11 · The manufacturer's word, attached
Reference Documents
Datasheets and installation manuals for the exact equipment specified. In a real approved set, these are often most of the page count.